阳光板雨棚的设计工艺主要有以下几点:
The design process of sunshine board canopy mainly has the following several points:
1、弹线:根据图纸的标高及阳光板顶棚位置尺寸和已测定的中心线,弹出阳光板顶棚丰骨架位置线。
1, elastic line: according to the elevation of the drawing, the
location of the ceiling and the central line, the ceiling line of the
sunlight board will be popped up.
2、预埋件:根据标高控制线阳光板顶棚主骨架位置,检查洞口反梁上表而标高是否符合设计要求,如有差异应剔凿或用高强度等级水泥砂浆找平处理,达到强度后,按深化设计节点详图预埋钢板尺寸放出膨胀螺栓位置线,然后钻孔安放膨胀螺栓,安装钢板与胀栓固定。
2, pre embedded parts: according to the position of the main frame
of the roof of the sun plate of the high control line, check the top of
the counter beam on the mouth of the hole or not to meet the design
requirements,jianchajingm.75ix.cn paishuiban.75ix.comreshuibeng.75ix.com
chilunbeng.75ix.com kaikouji.75ix.com songshuit.75ix.com if the
difference should be cut or the high strength grade cement mortar is
leveled, after the strength is reached, the position line of the
expansion bolt is released according to the detail drawing of the design
node, and then the position line of the expansion bolt is released.
Then, the position line of the expansion bolt is released. The expansion
bolt is installed in the drill hole, and the steel plate and the
expansion bolt are fixed.
3, install the main frame: according to the location of the main frame of the sun board.
4、安装次骨架:在阳光板顶棚主骨架安装固定完毕后,安装阳光板顶棚的骨架,并调准位置,调平后,与主骨架焊接固定。
4, installation of the skeleton: after the main frame of the roof
of the sun board is fixed, the frame of the ceiling of the sun board is
installed and the position is adjusted. After leveling, it is welded and
fixed with the main skeleton.
5、安装外层阳光板:按照深化设计排版位置,将准备好尺寸合适的阳光板进行安装。
5, install the outer layer of sunlight panels: according to the
deeper design layout, we will install the appropriate size of the sun
panels.