阳光板的膨胀预留量是不是合理,板材的裁尺寸是不是合格,预留的膨胀间隔是否均匀是否足够。膨胀间隙的相关数据可以找厂家提供帮助。
First, it is necessary to check whether the expansion of the sun plate
is reasonable, the size of the plate is not qualified, whether the
reserved expansion interval is adequate or not. The related data of the
expansion gap can help the manufacturer.
二,在将阳光板与配件安装固定的时候,最好将保护膜撕开30mm到50mm,这样是为了避免配件压条将保护膜压住。不过要注意的是不能揭的太多,不然容易因为安装操作划伤阳光板。
Two, when installing the sun plate and accessories, it is best to tear
the protective film 30mm to 50mm, so as to avoid the protection of the
protective film. However, it should be noted that too much can not be
uncovered, or it is easy to scratch the sun board because of the
installation operation.
三,如果阳光板有UV涂层,在安装时一定要注意分清,将抗紫外线的一面朝外安装,没有防紫外线涂层的一面朝内安装,切匆装错。
Three, if the sun plate with a UV coating in the installation must pay
attention to distinguish, the UV side outwards installation, no UV
coating is installed in the side, do not install the wrong cut.
四,如果是中空阳光板装置工程,板材连接的边缘局部最少都要保持20mm的空间,且阳光板装置工程相互连接的夹持配件至少要少一条筋肋。
Four, if the hollow solar panel device works, the edge of the plate
connection should be kept at least 20mm space, and the clamping device
of the sunlight panel device should have at least one rib.
五,配件安装好,在压实密封胶条和板材的时候连接件需要的自贡钉均匀的拧紧,不能用力过大,如果在因安装出错发生渗露,要及时用密封胶进行处理。
Five, the fittings are well installed. When compacting the sealant strip
and plate, the Zigong nail needed for the connection is evenly screwed
up. It cannot be exerting too much force. If the leakage occurs due to
the installation error, it must be treated with sealant in time.
六,如果需要自行对板材进行钻钉钻孔,一定要考虑到PC板的热胀冷缩性能和原理,合理的留出间隙。
Six, if you need to drill holes in the plate by itself, we must take
into account the thermal expansion and shrinkage performance and the
principle of the PC plate, and the reasonable clearance of the gap.
七,如果PC阳光板要进行冷弯安装,一定要注意冷弯的方向只能是顺着肋筋弯曲,同样,为了方便凝水流出,阳光板的倾斜装置也需要顺着肋筋方向,还需要注意的是阳光板的弯曲半径不能小于阳光板厚度的175倍。
Seven, if the PC sun board to install cold, must pay attention to the
direction of bending is only along the rib bend, similarly, in order to
facilitate the condensed water outflow, tilting device sunshine board
also need to follow the direction of the ribs, also need to pay
attention to is 175 times less than the plate bending radius not
sunshine sunshine plate thickness.
八,检查板材装置好后还有没有渗漏,检查所有需要注意的环节,包括外观,质量等等。
Eight, check the plate device after the leakage, check all the needs to
pay attention to the link, including the appearance, quality and so on.
九,安装过程中不能为图方便用脚踩踏阳光板面,一定要使用比较专业的进行跨移。
Nine, the installation process can not be convenient for the foot to
tread on the sun plate surface, must use a more professional cross
shift.
十,在确认安装发阳光板装置和配件后,方可撕开保护膜。如果遇到施工中必须要对阳光板进行保护时,也应该先撕掉,然后在覆
粪池模具 路缘石模具 唐山通风管道 塑钢电缆挂钩 钢纤维 钢制拍门 。
Ten, after the installation of the installation and accessories for the
installation of the sun plate, the protective film can be torn apart. If
you have to protect the sun board during the construction, it should be
tore off first, and then cover the protective film.